Manage Retention Money and Defect Liability Periods (DLP)

Tracking 5% retention escrow accounts, practical completion handovers, snag list rectification, and final retention release.

1. Overview & Business Value#

This comprehensive operational guide details the architecture, business workflows, configuration parameters, and execution steps for Manage Retention Money and Defect Liability Periods (DLP) within SmartERP.

Swimlane diagram of a sprint. The project manager or Scrum Master creates a sprint with dates and a goal. The team pulls backlog tasks in; if the project enforces the Definition of Ready and a task is not ready, SmartERP refuses with a message. Otherwise the sprint starts and SmartERP freezes committed hours and points. The team works the Kanban board. When the sprint is closed SmartERP freezes velocity and the completion rate.
A sprint from planning to close, and what SmartERP records at each end.

SmartERP Project Task Board and Milestones

Tracking 5% retention escrow accounts, practical completion handovers, snag list rectification, and final retention release.

2. Prerequisites & Security Access Groups#

  • Required Modules: project, smarterp_project_governance, hr_timesheet
  • Security Groups:
    • Project User (Technical ID: project.group_project_user)
    • Project Administrator (Technical ID: project.group_project_manager)
    • Timesheet Approver (Technical ID: hr_timesheet.group_hr_timesheet_approver)
  • Master Data Dependencies: Project master records, milestone stages, work breakdown structures (WBS), bill of quantities (BoQ), and employee billing cost rates.

3. Step-by-Step Configuration & Execution#

Step 1: Navigating to the Interface#

  1. Log into your SmartERP instance at https://smarterp.et/odoo.
  2. Open the main App Switcher (grid icon in the top-left corner).
  3. Navigate to Project → Projects.

SmartERP Project Task Board and Milestones

Step 2: Operational Data Parameters & Controls#

Ensure all mandatory parameters comply with enterprise operational standards:

  • Authorized Operator: Action executed under assigned RBAC permissions (Project Director, Project Manager, Agile Scrum Master, Lead Engineer).
  • Relational Integrity: Linked to upstream master records, approval requests, or transactional ledgers.
  • Statutory & Quality Controls: Verified against Ethiopian statutory regulations and corporate governance standards.

Step 3: Operational Execution & State Progression#

  • State Progression Gate: Advance record from Draft through Audited to Confirmed / Certified.
  • Integrated System Impact: Automatically updates real-time operational states and posts financial/inventory journal moves.
  • Audit Verification: System registers tamper-evident audit records logging user ID, timestamp, and cryptographic transaction digests.

Retention Money Governance#

Under standard Ethiopian public and commercial construction contracts, the employer withholds 5% of gross certified earnings from every IPC as a performance security.

The Two-Stage Retention Release Lifecycle#

  1. Practical Completion (Substantial Handover):
    • The consultant issues the Taking-Over Certificate (TOC).
    • First 50% of retention money (2.5% of total contract value) is released to the contractor (or exchanged for a Retention Bank Guarantee).
  2. End of Defect Liability Period (Final Completion):
    • Typically 365 calendar days following practical completion.
    • The joint inspection team reviews the snag list.
    • Upon rectifying all latent defects, the consultant issues the Final Completion Certificate.
    • The remaining 50% of retention money is disbursed.

Procedure: Processing Retention Release#

  1. Navigate to Projects > Construction > Retention Escrow.
  2. Open the project retention ledger.
  3. Click Release Retention Installment.
  4. Select Stage 1: Taking-Over Certificate.
  5. SmartERP automatically generates the retention invoice and updates general ledger account 110450 Retention Receivable.

4. Advanced Configuration Points#

  • Automated Actions & Scheduled Tasks (Crons):
    • Project: Flag overdue milestone deadlines (project.ir_cron_overdue_tasks): Runs daily to notify project managers of pending schedule delays
    • Timesheets: Send unsubmitted reminder alerts (hr_timesheet.ir_cron_timesheet_reminder): Runs weekly on Friday afternoon to remind team members
  • Custom Print Templates & Reports:
    • Project Status & Milestone Execution Scorecard
    • Interim Payment Certificate (IPC) for Construction
    • Project Timesheet & Resource Utilization Summary
    • Earned Value Management (EVM) Financial Report
  • Multi-Company Rules: Record-level security isolation under Company 1 (Ashewa Technology Solutions S.C.), preventing cross-company ledger leakage across parent and subsidiary legal entities.

5. Comprehensive Troubleshooting Matrix#

Error Symptom / ExceptionProbable Root CauseCorrective Action / Resolution
Access Rights Error: Cannot view confidential taskUser is not listed as a project follower or team member.Add user to Project Privacy Settings or Collaborators tab.
Validation Error: Timesheet date outside active stageAttempting to log labor against a closed or cancelled milestone.Select an active task stage or request reopening of the target work package.
Billing Rate Error: Missing employee cost rateAssigned employee lacks an hourly labor cost rate on their profile.Configure the employee hourly cost rate under Human Resources → Employees → HR Settings.