Construction Troubleshooting and Contractual Disputes
Resolving BoQ over-measurement flags, IPC deduction calculation discrepancies, negative retention balances, and dispute resolution.
1. Overview & Business Value#
This comprehensive operational guide details the architecture, business workflows, configuration parameters, and execution steps for Construction Troubleshooting and Contractual Disputes within SmartERP.


Resolving BoQ over-measurement flags, IPC deduction calculation discrepancies, negative retention balances, and dispute resolution.
2. Prerequisites & Security Access Groups#
- Required Modules:
project, smarterp_project_governance, hr_timesheet - Security Groups:
Project User(Technical ID:project.group_project_user)Project Administrator(Technical ID:project.group_project_manager)Timesheet Approver(Technical ID:hr_timesheet.group_hr_timesheet_approver)
- Master Data Dependencies: Project master records, milestone stages, work breakdown structures (WBS), bill of quantities (BoQ), and employee billing cost rates.
3. Step-by-Step Configuration & Execution#
Step 1: Navigating to the Interface#
- Log into your SmartERP instance at
https://smarterp.et/odoo. - Open the main App Switcher (grid icon in the top-left corner).
- Navigate to Project → Projects.

Step 2: Operational Data Parameters & Controls#
Ensure all mandatory parameters comply with enterprise operational standards:
- Authorized Operator: Action executed under assigned RBAC permissions (Project Director, Project Manager, Agile Scrum Master, Lead Engineer).
- Relational Integrity: Linked to upstream master records, approval requests, or transactional ledgers.
- Statutory & Quality Controls: Verified against Ethiopian statutory regulations and corporate governance standards.
Step 3: Operational Execution & State Progression#
- State Progression Gate: Advance record from Draft through Audited to Confirmed / Certified.
- Integrated System Impact: Automatically updates real-time operational states and posts financial/inventory journal moves.
- Audit Verification: System registers tamper-evident audit records logging user ID, timestamp, and cryptographic transaction digests.
Common Construction Operation Issues#
Issue 1: IPC Measurement Rejected with 'Quantity Exceeds BoQ Allowance'#
- Cause: Measured cumulative quantity in the IPC exceeds the contractual tender quantity without an approved Variation Order.
- Solution: Verify whether a Variation Order (VO) was issued. If yes, link the approved VO reference in the BoQ line item to increase authorized volume. If no, adjust measured quantities to match verified site surveys.
Issue 2: Advance Payment Deduction Out of Sync#
- Cause: Advance payment recovery formula was manually edited or percentage was calculated on net instead of gross certificate value.
- Solution: Open the contract settings. Verify that
Advance Recovery Baseis set toGross Certified Work. Recalculate the IPC draft.
Issue 3: Duplicate SIV Requisitions for Same Structural Element#
- Cause: Two separate site foremen submitted material requisitions for the same concrete pour.
- Solution: SmartERP flags element duplicates. Site Storekeepers must check the Requisition History by Work Element tab before validating physical material release.
4. Advanced Configuration Points#
- Automated Actions & Scheduled Tasks (Crons):
Project: Flag overdue milestone deadlines(project.ir_cron_overdue_tasks): Runs daily to notify project managers of pending schedule delaysTimesheets: Send unsubmitted reminder alerts(hr_timesheet.ir_cron_timesheet_reminder): Runs weekly on Friday afternoon to remind team members
- Custom Print Templates & Reports:
- Project Status & Milestone Execution Scorecard
- Interim Payment Certificate (IPC) for Construction
- Project Timesheet & Resource Utilization Summary
- Earned Value Management (EVM) Financial Report
- Multi-Company Rules: Record-level security isolation under Company 1 (
Ashewa Technology Solutions S.C.), preventing cross-company ledger leakage across parent and subsidiary legal entities.
5. Comprehensive Troubleshooting Matrix#
| Error Symptom / Exception | Probable Root Cause | Corrective Action / Resolution |
|---|---|---|
Access Rights Error: Cannot view confidential task | User is not listed as a project follower or team member. | Add user to Project Privacy Settings or Collaborators tab. |
Validation Error: Timesheet date outside active stage | Attempting to log labor against a closed or cancelled milestone. | Select an active task stage or request reopening of the target work package. |
Billing Rate Error: Missing employee cost rate | Assigned employee lacks an hourly labor cost rate on their profile. | Configure the employee hourly cost rate under Human Resources → Employees → HR Settings. |