Adjudicate award and manage standstill
Award contract to highest-scoring bidder, issue statutory Notice of Intention to Award, and govern the 7-day standstill cooling-off period.
1. Overview & Business Value#
This comprehensive operational guide details the architecture, business workflows, configuration parameters, and execution steps for Adjudicate award and manage standstill within SmartERP.


This guide explains how to finalize tender adjudication and enforce the statutory standstill cooling-off period.
2. Prerequisites & Security Access Groups#
- Required Modules:
purchase, stock, smarterp_store_voucher, purchase_requisition - Security Groups:
Purchase User(Technical ID:purchase.group_purchase_user)Purchase Administrator(Technical ID:purchase.group_purchase_manager)Inventory User / Storekeeper(Technical ID:stock.group_stock_user)
- Master Data Dependencies: Product masters, units of measure, approved supplier catalog, warehouse storage locations, and procurement budget lines.
3. Step-by-Step Configuration & Execution#
Step 1: Navigating to the Interface#
- Log into your SmartERP instance at
https://smarterp.et/odoo. - Open the main App Switcher (grid icon in the top-left corner).
- Navigate to Purchase → Tenders → Award Adjudications.

Step 2: Operational Data Parameters & Controls#
Verify that mandatory and statutory fields are populated in accordance with enterprise policies:
- Designated Authority / Actor: Operating under verified RBAC role (Procurement Endorsement Committee, General Manager, Legal Advisor).
- Associated Transactional Documents: Bound to upstream requisition, tender package, or purchase order contracts.
- Statutory Regulatory Validation: Strict adherence to Ethiopian Public Procurement Guidelines, Customs declarations, or Ministry of Revenue tax rules (VAT Proclamation 1157/2019, Withholding Proclamation 979/2016).
Step 3: Transactional Execution & State Progression#
- State Transition Gate: Progress the operational state from Draft through Audited to Confirmed / Posted.
- Double-Entry Financial Impact: Validated transactions automatically generate immutable accounting journal entries (
account.move) or stock move quant records (stock.move.line). - Audit Verification: System registers tamper-evident audit records logging user ID, timestamp, and cryptographic transaction digests.
Award Procedure#
- Open Purchase → Sourcing → Tender Adjudications.
- Select the completed tender. Review the ranked evaluation summary.
- Select Rank 1 bidder and click Adjudicate Award.
- SmartERP automatically generates the Notice of Intention to Award.
- The notice includes:
- Name of recommended awardee and contract price.
- Summary of scores for all qualified bidders.
- Reasons why other proposals were unsuccessful.
- Start and end dates of the statutory Standstill Period.
- Click Publish Award Notice. System emails notice to all bidders and starts the 7-day countdown timer.
Standstill Cooling-Off Period#
- The contract cannot be signed during the 7-day standstill period.
- SmartERP locks the tender; any attempt to generate a Purchase Order raises a validation block:
Standstill period active until [Date/Time].
4. Advanced Configuration Points#
- Automated Actions & Scheduled Tasks (Crons):
Procurement: Run scheduler (reordering rules)(stock.ir_cron_run_procurement): Runs daily to generate RFQs for inventory items below safety stockStock: Expired lot quarantine trigger(stock.ir_cron_quarantine_expired): Runs daily to isolate batches past shelf lifePurchase: Check supplier delivery deadlines(purchase.ir_cron_check_deadlines): Runs daily to send automated expediting notices to suppliers
- Custom Print Templates & Reports:
- Purchase Order Confirmation (Commercial Contract)
- Ethiopian Goods Receiving Note (GRN / Model 19)
- Store Issue Voucher (SIV / Model 20)
- Vendor Bid Evaluation & Comparison Matrix
- Multi-Company Rules: Record-level security isolation under Company 1 (
Ashewa Technology Solutions S.C.), preventing cross-company ledger leakage across parent and subsidiary legal entities.
5. Comprehensive Troubleshooting Matrix#
| Error Symptom / Exception | Probable Root Cause | Corrective Action / Resolution |
|---|---|---|
Access Rights Error: Cannot confirm Purchase Order | User lacks purchase manager approval privileges. | Escalate order to user with purchase.group_purchase_manager clearance. |
Validation Error: Stock move destination missing | Operation type lacks default internal destination location. | Configure target warehouse location in Inventory → Configuration → Operation Types. |
Quantity Mismatch: GRN vs PO 3-way match failed | Delivered quantity exceeds purchase order limit beyond allowable tolerance. | Verify physical delivery against supplier delivery slip and issue an amended PO or return voucher. |
Budget Reservation Error: Insufficient funds | Departmental budget allocation exhausted for target analytic account. | Submit a budget transfer or supplementary allocation request to the Finance Director. |